7.1.5 Restore to normal operation after “Load Off”

NOTE !

Make sure the UPS to be status of the activation of “Load Off”, i. e. UPS Output
Switch Q1
closed (Pos. I), Manual Bypass Switch Q2 (option) open (Pos. O) and
External Battery Switch or Fuses
connected (Pos. I).
If eBoost™
option is available, make sure that eBoost™ Operation mode is disabled
before starting this procedure.

View of the Synoptic Diagram after pressing the “Load
Off”
key.
All Contactors are open.
Rectifier, Inverter and Static-Switch shutdown.

LED Alarm is lit.



`

Home\Commands

COMMANDS

RESET TOTAL OFF

REQUEST LOAD OFF

V



1. Reset

Load Off.

Restore the command “Load Off” by entering the

screen: COMMANDS / RESET TOTAL OFF

• The Load is supplied by the Utility through the Automatic

Bypass.

Rectifier starts automatically, blinking LED 3 (Rectifier

ON) indicates Soft-start.

• At the end of Soft-start the LED 3 (Rectifier ON) remains

lit.

The Synoptic Diagram must display the statusLOAD
SUPPLIED BY AUTOMATIC BYPASS
.

2. Insert the Inverter by pressing the Inverter ON” ( I ) key.

Soft-start of Inverter indicated with blinking LED 5 (Inverter available).

At the end of Soft-start the LED 5 (Inverter available) remains lit.

Automatic transfer from Automatic bypass to Inverter.

LED Alarm turn Off and the LED Operation must be lit.

The Synoptic Diagram must display the statusLOAD

SUPPLIED BY INVERTER.

END OF PROCEDURE