4 COMPLETING THE INSTALLATION CHECKLIST

The final step in installing your battery cabinet is to complete the Installation Checklist. This checklist ensures

that you have installed all hardware, cables, and other equipment. Completing all items on the checklist will

ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain the

original. After completing your installation, a GE Service Representative will be able to verify the operation of

your battery cabinet, and commission it to support your critical load. The service representative cannot

perform any installation tasks other than verifying that the battery cabinet has been correctly installed. Service

personnel may request a copy of the completed Installation Checklist to be sure you have completed all

applicable equipment installation requirements.

NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for the first time.