Installation and O&M manual for SG battery cabinets - OPM_SGS_XXU_ISG_BAT_XUS_V020.doc

Installation Guide SG Series UL Battery cabinets

Startup Contact INFORMATION:

Date: ____________ Requested start up date: ____/____/____ Time: ______________

GE Zenith Sales Rep:________________________ Phone Number:___________________

Company name: ___________________________________________________________

Site Contact:_______________________________________________________________

Telephone #_______________Fax #_______________ E-mail_______________________

Facility/ End User Information:

Name ________________________________________________
Address

________________________________________________

City, State, Zip ___________________________________________

Contact ________________________________________________

Phone _____________ E-mail ____________________________

EQUIPMENT INFORMATION:


UPS Model #:

____________________________________

UPS Serial #:

____________________________________

INSTALLATION INFORMATION:


UPS / Battery

1. For 400/500 kVA UPS Only. Facing the back of the UPS, there are shipping restraints (yellow shipping

brackets and bolts) connected to the top inductor on the left side of the UPS. This bracket and

hardware must be removed prior to placing the UPS in its final installation location. Yes__ No__ N/A__

2. All packing materials are removed from UPS and battery cabinet and each is placed in its final installed

position. ---------------------------------------------------------------------------------------Yes__ No__ N/A__

3. Adequate workspace and clearances are provided around UPS and battery cabinet per NEC code and

the UPS installation manual.-----------------------------------------------------------------Yes__ No__ N/A__

4. The area around the UPS is clean (dust free) and free of conductive particles or moisture. Airborne

conductive particles can cause malfunctions of the UPS and possible damage to the UPS and its

connected loads. -----------------------------------------------------------------------------Yes__ No__ N/A__

5. Air conditioning is installed and operating properly. It should be sized for the maximum heat rejection

from the UPS at full load operation and recharging batteries. If the UPS will operate for a long period

during a power outage, then the hot air must be exhausted from the UPS room. The exhaust fan

should be powered by UPS output power. Otherwise, the UPS and battery will overheat and shut off

prematurely and possibly damage the UPS or battery. ----------------------------------Yes__ No__ N/A__

6. UPS internal input and output switches are open until the UPS is started (commissioned) by authorized

personnel. (The exception is the internal bypass switch may be closed if load power must be

established before commissioning. Input phase rotation [must be ABC Clockwise] should be checked

prior to closing the internal bypass switch.)------------------------------------------------Yes__ No__ N/A__