9 installation checklist – GE Industrial Solutions SG Series UL LISTED BATTERY CABINETS User Manual

Page 30

Advertising
background image

Modifications reserved

Page 31/36

Installation and O&M manual for SG battery cabinets - OPM_SGS_XXU_ISG_BAT_XUS_V020.doc

Installation Guide SG Series UL Battery cabinets

9 INSTALLATION

CHECKLIST

SG Series UPS Pre-Start up Checklist
It is our goal to ensure a smooth and uneventful start up of your UPS System. In an effort to minimize the

impact of this essential procedure to your overall operations as well as to avoid incurring additional start up

charges, we have provided a checklist of items that must be performed by the installing contractor prior to the

actual start up date for the UPS. The electrical installation must be in accordance with NEC code. GE Digital

Energy does not accept responsibility for electrical work.

Please read this entire document, complete the tasks in this form that are applicable to your system, and return

to our office at the number provided below prior to the startup date*.

GE Digital Energy requires two-week notice and the completion of this document prior to scheduling the start

up. This document should be completed and faxed to 866-765-3595. Unless otherwise purchased, all start-

ups will be completed between 8am-5pm Monday through Friday. If two-weeks notice is not given, no

scheduling guarantees can be made and additional charges may apply.

CONTRACTORS: Please note that there may be additional charges and warranty validation issues if during

installation foreign matter (i.e. metal filings) are allowed to disperse throughout the UPS electronics. Care must

be taken to capture all scrap metal when cutting/punching holes for conduit or other connections. A minimum

4-hours charge (no maximum) will be assessed to clean any foreign matter from within the UPS prior to

commissioning. This activity may also include the replacement of fans or other damaged parts due to this

foreign matter. All the above actions must be paid prior to the validation of the warranty on any unit found to

contain foreign materials (i.e. metal filings).
THREE-WIRE KIT: If your UPS is supplied with a three-wire kit, it must be noted that the input transformer for

the bypass must be a solidly grounded WYE source. The rectifier can be supplied by a DELTA source (Dual

Input), but the bypass or single source input must always be supplied by a solidly grounded WYE source,
whether using a three-wire kit or not.
Training will be performed upon startup completion**. It is the end user’s responsibility to have personnel

available to attend the operator training at the time of startup.

Thank you.
*Please take note that if the site and UPS are not ready for Startup, GE Consumer and Industrial will

remove the Field Engineer from site. A flat rate of $1,120.00 USD will be charged to reschedule the site

visit.

**Training is performed at the end of startup. Additional charges may apply if return trips are required for

training.

Cancellation of the site visit must be done no later than two business days prior to the scheduled visit to

avoid cancellation charges. Standard business days are Monday thru Friday 8:00am to 5:00pm Central

Time.

THIS SECTION IS FOR GE POWER QUALITY USE ONLY:
Enter review information in technical support log under the start-up work order.

Date Reviewed:

Reviewed By (Print):

COMMENTS

Advertising