Model mt 3810 – Brooks Instrument MT3810 User Manual

Page 54

Advertising
background image

4-2

Model MT 3810

Installation and Operation Manual

X-VA-MT3810-eng

Part Number: 541B050AAG

December, 2008

Section 4 Maintenance

There is no routine maintenance required for the Models MT 3810
flowmeters. However should it become necessary to replace, adjust or
remove components of the flowmeter, specific recommendations must
be followed.

4-2 Meter Float Replacement and Cleaning

Float replacement procedures are dependent on the meter size,
connection type and fluid (gas vs. liquid) application. Please refer to the
appropriate section below for instructions along with Figures 4-1, 4-2 and
4-3 for referenced part numbers (#) appearing in parenthesis.

1. Flanged Connection
a. Size 7 (1/2") Flanged Liquid or Gas Service
1. Remove the meter from the process line and lay the meter horizontal

on a table.

2. With a small screwdriver, remove the spiral retaining ring (#1) from the

meter inlet.

3. Push the entire float assembly slowly downward and out of the meter

inlet by pushing from the top with a round bar stock (3/4" or 19 mm
diameter).

4. Remove the float snap-ring to clean individual float assembly parts.
5. Reassemble the meter by reassembling the float assembly and

inserting it into the bottom of the meter. Replace the spiral retaining ring
(#1) in the meter inlet.

b. Size 8 (1/2") Flanged Liquid Service
1. Remove the meter from the process line and lay the meter horizontal

on a table.

2. With small screwdriver remove the spiral retaining ring (#1) from the

meter inlet.

3. Loosen the float assembly with two screwdrivers one on each end of

the meter and turn to loosen the inlet and outlet screws (#2). Remove
inlet screw (#2) at the bottom of the meter.

4. Remove the guide vane (#3) at the bottom of the meter and gently push

the float assembly up and out the top/outlet side.