Waterside, Waterside 19, Precision air conditioning easicool™ ezre – Airedale EasiCool 6kW 64kW User Manual

Page 19: Main te nanc e, Maintenance

Advertising
background image

19

EasiCool EZRE Operational Manual 7610207 V1.0.0_02_2013

M

ain

te

nanc

e

Precision Air Conditioning

EasiCool™ EZRE

Service Tools / Test Equipment

Spanners

Manometer

Thermometer

Refractometer

Safety Equipment

Safety Glasses / Goggles

Gloves

Overalls

Maintenance

Waterside

Procedures

Binder Points

Binder points should be fitted to both the flow and return pipe work adjacent to the cooling coil.

Water Strainer

A water strainer must be fitted to the inlet side of the evaporator.
Failure to do so may result in severe damage and will void the AIREDALE warranty.

Water Flow Rate

Check that the design water flow rate is available to the unit. If not available do not turn unit on.

Waterside Pressure Drop

Measure the waterside pressure drop of the unit ensuring control valves are operating satisfactory.

Glycol Strength

Check and record the glycol type and strength. Low levels of glycol can cause freeze up problems when operating at

low temperatures or during the unit off state during cold ambient conditions.

Glycol concentration is measured by use of a Refractometer.

Waterside

Task

Frequency

3 Mths

12 Mths

60 Mths

Check pressure drop of water strainer. If

excessive clean the strainer.

Visually inspect pipe and pipework insulation.

Pipework clamps are secure.

Inspect for water leakage.

Check condition of Water / Glycol solution to ensure that the

system is protected against corrosion, scale and microbiological

fouling, ensuring maximum heat transfer efficiency.

Advertising