Maintenance Requirements
CABINET
Wash down cabinet using a mild detergent. Treat any paint damage or rust as
necessary.
ELECTRICAL
1
Check all electrical connections for signs of overheating or arcing.
2
Check all cables for signs of chafing or physical damage.
SERVICE CHECKS -
YEARLY
As three-monthly plus the following:-
1
Check all electrical connections for tightness.
2
Check all refrigeration connections with leak detector.