Installation data, Unit lifting, Ultima compact condensing units – Airedale Ultima Compact Condensing Unit 30kW - 450kW User Manual

Page 30

Advertising
background image

ULTIMA COMPACT

Condensing Units

30

Condensers & Condensing Units

Technical Manual : Part No 904-047 V1.4.0_02_2013

Installation Data

UNIT LIFTING

Employ lifting specialists.

Local codes and regulations relating to the lifting of this type of equipment should
be observed.

Use the lifting eye bolts/lifting lugs provided.

Attach lifting chains to the 4 lifting eye bolts/lifting lugs provided, each chain and eye
bolt must be capable of lifting the whole chiller.

Use the appropriate spreader bars/lifting slings with the holes/lugs provided.

Lift the unit slowly and evenly.

If the unit is dropped, it should immediately be checked for damage and reported to
Airedale Service.

CAUTION

Only use lifting points provided.

The unit should be lifted from the base and where possible, with all packing and
protection in position. If any other type of slinging is used, due care should be taken to
ensure that the slings do not crush the casework or coil.

LIFTING DIMENSIONS

A

C

B

E

D

UCCU30 - 80 (Except UCCU75)

A

B

(1)

C

(1)

D

(1)

E

1 FAN /1

mm

300

1050 (1450)

300 (300)

1900 (2200)

1270

2 FANS /1

mm

300

1450

750

2200

1270

E

A

B

C

D

UCCU75 - UCCU450 (Except
UCCU80)

A

B

C

D

E

75, 100, 125 & 150

..-2/1

mm

290

1900

585

2500

1450

..-3/1

mm

290

2015

1320

2500

1450

..-4/1

mm

290

2870

1315

3000

1450

110, 130 ,160 ,180,
200, 225 & 250

..-4/2

mm

180

1580

605

2500

2000

..-6/2

mm

595

1650

925

2500

2000

..-8/2

mm

595

2050

1330

2500

2350

275, 300, 330, 360,
400 & 450

..-8/2

mm

465

2560

1625

3000

2350

..-10/2

mm

465

3135

1900

3500

2350

..-12/2

mm

465

3610

2275

3500

2350

..-14/2

mm

465

4385

2350

4000

2350

..-16/2

mm

465

5035

2550

5000

2350

Advertising