Preventive Maintenance Instructions

35

M412060

Every Six Months

Lint Removal and Cylinder Belt Inspection

Drive System

1. Remove belt guard cover.

2. Clean the lint and any other foreign materials

from the air vents located on the front and back
of the drive motor. The drive motor is air cooled
and if the air vents become clogged, the motor
will overheat and the internal thermal overload
protector will cycle off.

3. Reinstall belt guard cover.

Front Panel

1. Remove front panel by removing lint drawer and

loading door. Remove fastening screws for front
panel, disconnect control housing, terminal
blocks.

2. Pull front panel out. Remove any lint that has

accumulated in the corner of the inside. Use a
vacuum where possible or a small brush.

3. The poly-v cylinder belt tension is automatically

set by a spring loaded idler system. There is no
adjustment. The belt should show no signs of
excess wear or cracking. If it does, replace with a
genuine service replacement.

4. Inspect the belt tensioning idler assembly. The

idler arm should move freely (with considerable
belt-spring tension [approximately 40 pounds])
and should not bind in any position between
stops.

5. Clean lint off any of the idler assembly parts.

6. Reassemble the front panel by lifting and placing

the panel at its edge resting on the machine front.

7. Reach in through door opening, and connect the

terminal blocks to each control housing.

8. Push the front panel into place and line up holes.

9. Insert corner screws first and then remaining

screws. Tighten all screws.

10. Reinstall lint drawer, pressing it firmly against

the front panel and locking it.

11. Reinstall loading door.

Overall Check

Check the tumbler over thoroughly for loose nuts,
bolts and screws and for loose gas and electrical
connections.

To reduce the risk of serious injury,
disconnect power to the tumbler before
performing this operation.

W657

WARNING

To reduce the risk of fire or electric shock,
electrical connections such as electric
service and grounding connections should
be examined for proper torque a week after
initial installation, again after a month of
operation and thereafter every six months.