Receiving & Installation 3-5

MN2417

Single Phase Connections

Single phase connections are made at load receptacles located by the operator panel, see

Figure 3-3. Simply open the rear panel access door and make the connections. When the panel

door is closed, the connections are weather tight.

Figure 3-3 Receptacle Panel (Single Phase)

Single phase power is
always available.

(GOLD)

X

(GOLD)

Y

G

(SILVER)

W

CS6369

125/250V

50A

X

Y

W

Test

Reset

CS6365N

GFI Outlet
120V, 20A

240V, 50A

Circuit Breakers (Single or Double pole)

Circuit Breakers provides protection on some
units. To reset a breaker, place it in the OFF
then the ON position.

Single pole breaker
for 120VAC outlets

Double pole breaker
for 240VAC outlets

Figure 3-4 Remote Start Connections

RR1 RR2

Remote Start Connections

Tier 1 Systems

Tier 2/3 Systems

Remote Start Connections on front panel