SECTION 3 -- INSTALLATION


Unpacking

Your new unit has been thoroughly packaged to avoid shipping damage. However, the
unit should be fully inspected upon arrival before signing for receipt. If the package has
visual damage, notes should be made on the freight bill and signed by the delivery
company. In the event of concealed damage after the unit is uncrated, keep the carton
and packaging material. Call the shipping company within 7 days of receipt, request
inspection and retain a copy of the inspection report.

Caron provides full on-site installation services for all models. Our installation services
guarantees the proper set-up and startup of all equipment. Please contact the Service
Department at 740-373-6809 or

[email protected]

for details.



Choosing a Location







To ensure proper operation, the unit must be located on a firm level surface, capable of
supporting approximately 500 pounds (1000 pounds if the units are to be stacked). The
unit should be located in an 18°C

– 25°C ambient area and where there is no direct

airflow from heating and cooling ducts as well as out of direct sunlight. Allow four inches
of clearance on all sides of the product to allow for connections and airflow.


The unit requires a dedicated electrical connection. Power requirements vary depending
upon the incubator model, see Connecting Electrical Power section.
Choose a location where these facilities are, or can be made available. If a water
source, or a drain is not available, contact CARON customer service and ask about our
CRYS102 product line or click this weblink for information on the product:

http://www.caronproducts.com/65



Preliminary Cleaning

This product weighs in excess of 400 pounds.
Ensure that sufficient resources are available to
safely move the product.

Advertising
This manual is related to the following products: