Ensure chassis is

connected to earth

ground.

POWER SUPPLY INPUT

120/208VAC, 3P4W, 1.3A, 60Hz

120/240VAC, 1P3W, 1.3A, 60Hz

EXTERNAL DISCONNECT REQUIRED

P1

If the connector needs to be moved, follow the following procedure:

First, remove the ten (10) #4-40 x 1/4” mounting screws that fasten the

lid onto the EDI-120 chassis. Remove the lid and set it aside, along

with the screws. Remove the metal cover plate on right-hand side P1

location by unscrewing the two (2) #4-40 x 1/4” mounting screws. Set

the cover plate aside, along with the screws. Release the P1 power

connector by carefully squeezing the tabs on each side of the connector

together and pushing the connector back. Cut and remove the wire-tie

securing the cable to the EDI-120 chassis via the bridge lance located

on the front-side of the chassis. The P1 connector/cable can now be

moved to the right-hand side location. Neatly route the cable and then

clip the P1 connector into place. Be sure the P1 connector is fully

seated and secure. Use a wire-tie to secure the cable to the chassis –

there is a bridge lance located above the power supply on the front-side

of the chassis. Reinstall the cover plate over the P1 connector opening

on the left-hand side of the chassis. Reinstall the lid.

• A 10’ (3m) yellow CAT 5e patch cable is supplied to daisy-chain the

DMX-A and DMX-B between multiple EDI-120 retrofit systems, in multi-

rack installations and racks containing more than 120 dimmer circuits. If

applicable, route the cable into place.

• Everything should now we prepared and ready for final installation of the

EDI-120 retrofit.

• Put the EDI-120 retrofit into a position where all the field wiring and

OEM wiring can be plugged in.

• Connect (plug in) in the green ground wire onto the EDI-120 chassis

connector.

• If applicable, connect (plug in) in the yellow CAT 5e patch cable.

• Connect (plug in) the prepared DMX input and thru connectors.

• Connect (plug in) the prepared input/output contacts connector.

• Connect (plug in) the prepared analog input connector.

• Connect (plug in) the prepared +12VDC power supply connector.

• Connect (plug in) the OEM P1 power connector.

• Connect (plug in) the OEM P3, P4, P5 and P6 ribbon cable connectors.

• All of the field wiring and OEM cables should now be connected

(plugged in).

• Be sure all connections are secure and fully seated.

• Slide the EDI-120 retrofit along the guide rails and into place. Be sure

not to pinch any of the cables.

On some earlier versions of EDI Mark VII dimmer racks, the guide rail

opening for the EDI-120 retrofit may be much narrower. If this is the

case, the guide rails will need to be removed. Once the guide rails are

removed, the EDI-120 retrofit will need to held in place and secured

using the mounting screws provided.

• Secure the EDI-120 retrofit using the four (4) #10-32 x 3/8” mounting

screws provided.