4 Start-up

882 Compact IC plus – Anion – MCS

■■■■■■■■

57

4 Start-up

The chapter Start-up is divided into 2 sections:

Initial start-up

The initial start-up is carried out during the ini-
tial installation
.

Conditioning

Conditioning is carried out as a final installation
step and each time after the system is started.

4.1

Initial start-up

The initial start-up is carried out during the initial installation. The entire
system is rinsed before guard column and separation column are installed.

Caution

The separation column and guard column may not be installed for the
initial start-up.

Make sure that the coupling (6.2744.040) is being used instead of the
columns.

Perform the following steps during the initial start-up:

1 Preparing the software

Start the PC program MagIC Net™.

Open the Equilibration tab in MagIC Net™.

Select (or create) a suitable method.

2 Preparing the instrument

Ensure that the eluent aspiration tubing is immersed in the eluent
and that there is enough eluent in the eluent bottle.

Ensure that the aspiration tubings for the auxiliary solutions
(regeneration solution and rinsing solution) are immersed into the
respective solutions and that the is enough solution in the bottles.

Switch on the instrument.

3 Starting equilibration

In MagIC Net™, start the equilibration.