Load cell installation, Parts list, Installing the load cell – Dynojet 224: Eddy Current Brake User Manual
Page 32: Parts list -2 installing the load cell -2
Model 224 Above Ground Eddy Current Brake Installation and User Guide
C H A P T E R 2
Load Cell Installation
2-2
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
LOAD CELL INSTALLATION
This section describes how to install the load cell.
P
ARTS
L
IST
The following table lists all of the parts included in the Torque Module Installation kit
(P/N 73920007). Check your kit against the parts listed to make sure you have
received all of the parts. If any part is missing, contact Dynojet Technical Support.
I
NSTALLING
THE
L
OAD
C
ELL
1
Verify the main dyno power is disconnected.
2
Remove the two bolts and nuts securing the existing bar on the eddy current
brake and remove the bar. Set the bolts and nuts aside.
3
Verify the eyelets on the load cell are spaced the same as the bar removed earlier.
Adjust the load cell spacing by loosening the lock nut and turning the eyelet.
Figure 2-1: Verify Load Cell Spacing
part number
description
quantity
35430899
Weight, 25 lb
4
61319001
Calibration Arm Assembly
1
66114002
or
66104001
Torque Module Sub-Assembly
or
Torque Module High Resolution Sub-Assembly
1
76950505
Torque Cell Assembly, 224
1
76950606
Cable, Input, 224 Torque Rev Sw
1
76950607
Cable, Output, 224 Torque Rev Sw
1
distance must be
the same
eyelet
bar
lock nut