Installation

3

2.0

Installation

This section describes procedures for installing the foundation and weighbridge for of the Survivor

®

PL railroad

track scale.

2.1

Foundation Installation

Please reference foundation drawings supplied by Rice Lake Weighing Systems for the scale you have purchased.

Do not start construction of the foundation if you do not have certified prints.

1. Pour the scale slab(s).
2. Pour the approach slab and, if applicable, dead slab over rebar or optional anchor bolts.

Note

Anchor bolts should protrude from the concrete enough for the lower base plates to be secured onto them.

2.2

Weighbridge Installation

The following steps describe the procedure for installing the Survivor

®

PL weighbridge.

1. Set load cell lower base plates over the pre-cast anchor bolts.
2. Install leveling bolts into base plates as shown in Figure 2-1.

Leveling bolts

Load cell lower
base plate

Anchor bolts

Figure 2-1. Leveling Bolts Installed into Lower Base Plate

3. Install load cell, spacer plate, and base plate onto lower base plates.

Load cell

Load cell base plate

Load Cell Installed

Load cell spacer plate

Figure 2-2. Load Cell, Spacer Block, and Base Plate