Wooden setting
block
Installation
5
Figure 2-5. Weighbridge Module on Setting Blocks
8. Using a jack and shims, level the module and set its elevation between 2 1/8” and 2 1/4” above concrete
approaches.
Figure 2-6. Module Elevation
9. Using leveling bolts, raise and level the load cell assemblies to contact the upper mount bearing plates.
Jack
Load cell
leveling bolts
Upper load cell
mount plate
Figure 2-7. Load Cell Assembly
10. Jack the weighbridge to allow removal of setting blocks and shims.
11. Install lower base plate washers and nuts.
Note
Do not torque nuts until after plates are grouted.
12. Install check rods and hardware. Set check rods level with a horizontal plane to within +/- 2 degree.