Attempting to obtain power from the machine terminals may damage the ma-
chine circuit and/or the chemical injection system. Consult the chemical injec-
tion supply system instructions for operational details.

Figure 4.19: External Chemical Supply Terminal Block Detail

7. For testing, select program 30 by pressing key 3 and key 0 on the keypad. Then press ENTER

followed by the START key. Run the complete program, checking operation of water inlet
valves, drain, and extract functions. Program 30 is a test program that goes through most
machine functions. Please note that the Spin 99 routine is designed to fail balance. Simply
advance the program to the Spin 3 cycle after balance fails (use the appropriately named
ADVANCE key). Refer to the EL6 Stock Program Listing that came with the machine for
further details on the test program.

8. Cylinder rotation must be counter-clockwise in the extract step. If rotation is not correct,

disconnect the power to the machine. A qualified technician must reverse any two leads
between the AC drive and the motor. See figure 4.20 on page 40.

Figure 4.20: Inverter Drive to Motor Detail