9171 Installation Guide

Proprietary & Confidential

Canoga Perkins Metro Ethernet Routing Switch

Page 14 of 26

When there is no grounding bar in the installation environment of Ethernet switches and grounding electrodes
are not permitted to bury according to the conditions, if Ethernet switches are supplied with AC power, they
can be grounded through PE cables of AC power. At this point, PE cables of AC power should be confirmed
well grounded in the power distribution room or on AC supply transformer side.

Fig. 2-7: Grounding Installation Sketch Using AC PE Cable

Description:

(1) Power input of switch

(2) Ground terminal of switch

(3) Power transformer

(4) PE

(5) 3-core cable used in AC power connection

(6) Switch

2.3.3 Post-Installation Checking

Check if selected power agrees with the identified power of switch:

Check if the ground wire is connected.

Check if the connections between configured cables and power input cables are correct.

Check the interface cables are arranged indoors instead of outdoors, if some cables are arranged
outdoors, check if they are connected with an AC power lightning protection strip and network port
lightning protector.