SECTION 2.
Installation Instructions

2A. General Information

WARNING

Follow local regulations with respect to installation
of carbon monoxide (CO) detectors and
manufacturer's maintenance schedule of the boiler.

Install the HH-PH boilers in accordance with the

procedures in this manual (or the Laars warranty may

be voided), local codes and ordinances. In the absence

of such codes, install the boilers in accordance with

the latest edition of the National Fuel Gas Code, ANSI

Z223.1. In Canada, the installation must be in

accordance with CAN1-B149.1 or .2 and local codes.

The authority having jurisdiction may require the

installation conform to the Standard for Controls and

Safety Devices for Automatically Fired Boilers,

ANSI/ASME CSD-1. Any changes to the boiler, gas

controls, gas orifices, wiring or draft hood may void

the warranty. If field conditions require change,

consult the factory.

All gas-fired products require correct installation

to assure safe operation. The requirements for boilers

include the following:
1.

Field assembly of draft hood and vent cap

(if required – see Section 2B)

2.

Appropriate site location (clearances) and

flooring

3.

Sufficient combustion and ventilation air

4.

Adequate venting of combustion products

5.

Adequate water flow

6.

Properly sized gas meter and piping

7.

Proper electrical wiring
This manual provides the information needed to

meet these requirements. Review all application and

installation procedures completely before continuing

the installation.

2B. Field Assembly

The HH-PH boiler is shipped from the factory

with the top assembly in the low-profile configuration

for outdoor installations.

The HH-PH boiler is design certified for indoor

installation when equipped with a drafthood, which

must be installed without modification. Check the

rating plate on the boiler for the correct Laars part

number.

Follow this procedure to make the conversion:

a.

Remove the top filler plate, stamped “HOT,” by

slipping a fine-blade screw driver into the slot at

the rear of the plate and gently prying it up (see

Figure 2).

b.

Remove the two screws attaching the adapter

plate to the top assembly and lift it out (see

Figure 3).

c.

Remove the vent cap or drafthood from its

package.

d.

Disengage the flue transition ring from the stack

extension and place it on top of the collector

assembly as shown in Figure 4.

Figure 2. Top Filler Plate.

Figure 3. Adapter Plate.

Figure 5. Vent Cap with

Adapter Plate

Figure 4. Flue Transition

Ring.

e.

Slide the adapter plate over the bottom of the

stack extension as shown in Figure 5. Fit the

stack extension down over the flue transition

ring. Seat the adapter plate on the top assembly

and secure it with two screws (see Figure 6).

f.

Find the vent damper box which is located in the

boiler package (boiler models 175 to 250 only)

(see Figure 8).

g.

Install the vent damper directly to the top of the

draft hood outlet. The damper operator should

face to the front of the boiler, and the flow

direction arrow should point upward. Use the

vent damper wire harness to connect the vent

damper to the boiler. The bracket end of the

harness should be connected to the vent damper

actuator.

Advertising