B* V*nt Termination

Only a termination tee with debris screen is
allowed for vent termination. See Section
D., Vent Termination Tee Instailation for
allowable termination tee.

NOTE: Terminating vent system with other

than terminating tee can cause im­
proper furnace operation. See Fig­

ure 8 for proper vertical vent termi­
nation.

Vent this furnace using these instructions,

Installers' Information Manual and Part 7 of
Current National Fuel Gas Code ANSI

2223.1/NFPA 54. Also, meet requirements
of local utilities and other local code authori­
ties.

PIPE STORM COLLAR

PUSHING

SIZE OF OPENING VARIES
ACCORDING TO THE PITCH OF THE ROOF.
NEED 5" MIN. AIR SPACE FOR 3“ PIPE
NEED 9“ MIN. AIR SPACE FOR 4" PIPE

FIRESTOP

CHASE: •5" AIR SPACE REQ'D. BETVi/EEN
3" PIPE AND COMBUSTIBLE MATERIAL.

*9" AIR SPACE REQ’D. BETINEEN

4" PIPE AND COMBUSTIBLE MATERIAL.

*SEE SECTION B. "PLANNING THE INSTALLATION'

Figure 8