General Installation Recommendations

Installation

Ferrites

The ferrites prevent high frequency electrical noise (radio frequency interference) from exiting or entering the

equipment. You can locate the loose ferrites (where applicable, check Contents of Package chapter in the user

manual) in the Accessories box which are part of the main computer unit packaging. Some products have also factory

mounted ferrites on internal connectors (where applicable).

The ferrites must be mounted on specificed cables to fully comply with the Type Approvals.

Step 1 / 2 : Preperation

The ferrites should be mounted (clipped in place on the cable) and

located as close as possible to the connector piece that connects to

the rear of computer (maximum length from computer connector is

5cm [1.97 inch]). See checklist below.

When ready: Open the ferrite, place the cable inside as shown in

FIG1, and then gently close it until a click can be heard (FIG2). You

may close and re-open them as many times as required during the

installation.

Step 2 / 2: Checklist

Typenumber

Ferrites for Cables

Dimetric View

Perferred distance / location of ferrites. Computer shows side view

HM C01 STx-D601

HM C01 STx-D602

x=Operating System

16 x Würth 742 711 12:

For USB, Audio, COM,

Keyboard and Mouse

4 x Würth 742 711 31:

For Ethernet

1 x Würth 742 712 21:

For Parallel

Red Line indicate 5cm [1.97 inch] limit from connector (black square).

Do not mount ferrites (orange square) located beyond the red line!

Note: If you have many cables, mounting ferrites might have to be

arranged as a alternating stair-step like pattern. This is to prevent clumps

of ferrites that might apply tension to the connected connectors.

FIG1

To computer

FIG2