Field connected water piping, Closed loop tower/boiler systems, Open loop well water systems – WaterFurnace Series NXW User Manual

Page 10: Earth coupled systems

Advertising
background image

10

ENVISION

2

NKW 50Hz REVERSIBLE CHILLER INSTALLATION MANUAL

General

System piping should be kept as simple as possible to

minimize the pressure drop, but hand valves should be field

installed to facilitate unit servicing. The piping installation

should provide service personnel with the ability to measure

and/or monitor water temperatures and pressures.

Source and load fluid connections are provided with 2-inch

[50.8mm] Victaulic grooved nipples (see Figure 4). Each

nipple will also have a PT port installed for test and balance

purposes. It will be the installing contractor’s responsibility

to adequately support incoming piping to avoid damage to

the unit’s piping or heat exchangers. The water lines should

be routed so as not to interfere with access to the unit.

For any installation where the transmission of vibration

through the piping connections could cause unacceptable

noise levels in occupied spaces it is important to provide

adequate vibration damping.

NOTE: Units are factory run-tested using propylene

glycol. Prior to connecting piping to unit, thoroughly flush

heat exchangers.

Before final connection to the unit, the supply and return

hose kits must be connected to each other, bypassing

the unit, and the system flushed to remove dirt, piping

chips and other foreign material. Normally, a combination

balancing and close-off (ball) valve is installed at the return,

and a rated gate or ball valve is installed at the supply. The

return valve can be adjusted to obtain the proper water

flow. The valves allow the unit to be removed for servicing.

The proper water flow must be delivered to each unit

whenever the unit heats or cools. The proper flow rate

cannot be accurately set without measuring the water

pressure drop through the refrigerant-to-water heat

exchanger. A 3 GPM flow rate per ton [0.054 LPS per kW]

of cooling capacity (2.25 GPM per ton [0.0404 LPS per

kW] minimum) is required.

NOTE: The placement and connection of the water

circulating pump(s) must be taken into consideration prior

to designing the final water piping systems.

Field Connected Water Piping

CAUTION: Remove the plastic protective caps in the ends of each of the four water pipes on the heat

exchangers prior to piping connection. Failure to remove the caps will result in serious damage and could void

the warranty.

Closed Loop Tower/Boiler Systems

The water loop is usually maintained between 60°F [15.5°C]

and 90°F [32.2°C] for proper heating and cooling operation.

This is accomplished with a cooling tower and a boiler.

To reject excess heat from the condenser water loop, the

use of a closed-circuit evaporative cooler or an open type

cooling tower with a secondary heat exchanger between

the tower and the condenser water loop is recommended.

If an open type cooling tower is used without a secondary

heat exchanger, continuous chemical treatment and filtering

of the water must be performed to ensure the water is free

from damaging materials.

CAUTION: Water piping exposed to outside

temperature may be subject to freezing.

Open Loop Well Water Systems

Installation of an open loop system is not recommended

without using a secondary heat exchanger unless water

quality guidelines are met.

Earth Coupled Systems

All supply and return water piping should be insulated to

prevent excess condensation from forming on the water

lines. Ensure pumping system is capable of providing

adequate flow rate at the system pressure drop, 3.0 GPM

per ton [0.054 LPS per kW] (source side) is recommended.

Antifreeze in the loop is strongly recommended.

Advertising