EMI Volts/HZ/pH User Manual

Page 9

Advertising
background image

www.enviromaster.com

Side Discharge Condensers

9

inStallation inStrUCtionS

reFrigerant piping

Continued

2. Protect the valves by wrapping with a

wet rag "heat sink" before brazing.

3. We recommend the use of a shield (can

be made from some scrap metal) to

protect the paint.

4. Braze tubing into fittings.

1. Clean the ends of tubing and insert into

fittings.

5. Attach manifold set.

6. Evacuate line to 500 microns or less to

ensure all moisture has been removed

and there are no leaks.

Refrigerant

refer to refrigerant

Charge table for

specified line charge.

7. Once certain of a good evacuation and

leak free joints, back-seat the valves

(counter-clockwise) to open and allow

factory charge to fill lines and indoor unit.

S1C
Shown

S1C
Shown

S2C
Shown

S1C
Shown

S1C
Shown

Manifold

Vaccum Pump Micron Gage

manifold Setup For evacuation

S1C
Shown

S2C