10kva single phase version – Riello UPS Sentinel Dual (High Power) (3.3 - 10 kVA) User Manual

Page 65

Advertising
background image

65

U

SE

8-10kVA single phase version

1. Use 3 cables with 10 mm

2

section (EARTH, N and

L) in input, and 3 cables with 10 mm

2

section for the

output (EARTH, N and L). With reference to the
figure shown at the side:

- Insert the cables from the 63A magneto-thermal

switch into seal stop P2 (input line).

- Insert the cables from the load into seal stop P1

(output line).

- Strip the cables observing the measurements

provided.

- Insert the part that has just been stripped into the

ferrules provided.




2. Connect the wires to the relative terminals

strictly following the instructions set out
below:

Input line

a - Ensure that the magneto-thermal switch

upstream is open.

b - Connect the earth wire to terminal 3.

c - Connect the neutral wire to terminal 1.

d - Connect the phase wire to terminal 2.

Output line

a - Connect the earth wire to terminal 6.

b - Connect the neutral wire to terminal 7.

c - Connect the phase wire to terminal 8.

Bypass line
a - Ensure that a jumper is connected at

terminals 9 and 10; this is needed for the
correct operation of the UPS.