MAYCO ST-45HRM CE PUMP — OPERATION & PARTS MANUAL — REV. #0 (02/23/04) — PAGE 55

ST-45HRM CE CONCRETE PUMP— MAINTENANCE (PUMP)

Figure 55. Accumulator Circuit Pressure Test Gauge

UNLOADING

VALVE CARTRIDGE

LOCK NUT

ADJUSTMENT

SCREW

Figure 56. Unloading Valve Cartridge Adjustment

SETTING PRESSURE IN THE ACCUMULATOR CIRCUIT

1. Attach a

20.68 mPa (3,000 psi)test gauge

(Mayco P/N

98016) to port

G2

of the main manifold block (Figure 55).

2. Loosen the lock nut on the

unloading valve cartridge

(Figure 56) and using an allen wrench, turn the adjusting
screw

clockwise

until it is completely closed.

3. Turn the

pump control switch

(Figure 22) to the “ON

position and run engine at 2,550 RPM.

4. Loosen the lock nut for the the accumulator circuit

pilot

relief valve cartridge

(Figure 57), located at port

G4

. Using

an allen wrench, turn the adjusting screw until pressure
gauge reads 13.44 mPa (1,950 psi) and tighten lock nut.
Turn the engine off and on several times to make the
pressure continues to read 13.44 mPa (1,950 psi).

5. Turn the

unloading valve cartridge

adjusting screw

counter-clockwise

until the pressure reaches 12.07 mPa

(1,750 psi)

on the accumulator pressure gauge (Figure 29).

Start and stop the pump several times to make sure the
accumulator circuit pressure is holding at 12.07 mPa (1,750
psi).

6. Tighten the lock nut on the unloading valve cartridge. Your

accumulator circuit pressure should now be properly
adjusted.

Figure 57. Pilot Relief Valve Cartridge Adjustment

PILOT RELIEF

VALVE CARTRIDGE

LOCK NUT

ADJUSTMENT

SCREW