Water Connections

1. Connect the hot water supply to the fill hose provided with a 3/4" NPT fitting.
2. Install a manual shut-off valve in the water supply line to accommodate servicing the

machine. The shut-off valve should be the same size or larger than the supply line and

installed as close to the dishwasher as possible.

3. Install a 3/4" pressure reducing valve (PRV) (supplied with machine) in the water supply

line, and set at 20-22 PSI/138-151kPa. Install the PRV downstream from the service

shut-off valve and as close to the dishwasher as possible.

Drain Connections

1. Drain hose must be supported by bracket provided (shipped inside of machine).
2. The drain hose bracket must be mounted a minimum of 2 feet above the finished drain,

either on the rear of the machine or on the wall.

3. The maximum height of the drain from the floor must not exceed 3 feet.
4. Connect the 3/4"I.D. flexible drain hose to a 1-1/2" wye (Y) drain fitting. Use a 3/4" hose

Plumbing Connections

Note:

Plumbing connections must comply with local health and plumbing codes.

Installation

Connect machine flexible

drain hose to a wye fitting.

Do not connect the machine

flexible drain hose to a

90° fitting.