5-10. Adjusting Wire (MIG) Weld Puddle Consistency

803 099

3/8, 7/16 in

Tools Needed:

1

3

2

Y Stop engine and let cool.
Stabilizer DC-Z is factory connected to suit

most Wire (MIG) welding applications.
To change Wire (MIG) weld puddle consis-

tency, proceed as follows:
Remove cover and right side panel.
1

Stabilizer DC-Z

2

Wire /CV Weld Output Terminal

3

Stabilizer Leads 29, 28, And 27
Lead 29 − provides stiffest weld

puddle
Lead 28 − provides wetter weld

puddle (for mild steel)
Lead 27 − provides wettest weld

puddle (for stainless steel)

Lead 29 is connected to the Wire/CV weld

output terminal at the factory.
Disconnect lead 29 from the Wire/CV weld

output terminal.
For wetter weld puddle (for mild steel):
Remove insulated sleeving from lead 28.

Connect lead 28 to Wire/CV weld output ter-

minal, reusing hardware. Insulate lead 29

with sleeving removed from lead 28. Secure

sleeving with cable ties.
For wettest weld puddle

(for stainless steel):
Remove insulated sleeving from lead 27.

Connect lead 27 to Wire/CV weld output ter-

minal, reusing hardware. Insulate lead 29

with sleeving removed from lead 27. Secure

sleeving with cable ties.
Reinstall side panel.