Section 2

Hardware Installation

10

2.2. Rackmount Installation

Before you start installation please verify that all

parts are included according to the package

contents.

If you want to install the KVM Switch in a 19” server

rack please attach the enclosed 19” rackmount

brackets using the screws provided.

2.3. Cascading / Daisy Chaining of multiple KVM Switches

At the time this manual was written (September 2007) the U8/16 KVM switch range may be

cascaded with other LINDY U-Series KVM switches only. Later versions of the new C5-8/16

series KVM switches will be introduced that will also be daisy chainable with the U series.

All other brands and models of KVM switches may be cascaded with LINDY U-series KVM

switches via the computer ports 1-16 of the U-series KVM switch.

To connect an additional SLAVE switch to the MASTER (or previous) switch, you must use the

included special KVM system daisy chain cable. Standard VGA cables may not work correctly

as not all cables support all pins connected.

Step 1 - Connect the local console

Connect your keyboard, mouse and monitor to the console ports of the U8/16 MASTER KVM

Switch.

Step 2 – Connect the first Slave

Use the daisy chain cable to connect the

daisy chain port

of the MASTER/previous KVM

Switch and the other end to the

local console port

of the next SLAVE switch.

Step 3 – Cascading / Daisy chaining

Repeat the previous step to daisy chain mores switches. Each individual switch in the chain

represents a different

Bank.

The MASTER switch is Bank 1 and each cascaded SLAVE follows

on as Bank 2, 3, 4 etc. You may cascade a maximum of eight switches/banks.


Bank 1 (Master)

Bank 3... to a maximum of 8

Cascading KVM Switches

by daisy chaining

Section 2

Hardware Installation

11

Step 4 – Resetting the Switches

After you have connected and switched on the SLAVE switches and computers, all of the KVM

switches may need to be reset. First, reset the SLAVE switch at the end of the daisy chain and

then reset all of the other SLAVE switches up to the MASTER U8/16 switch.

To reset the switch, press and hold the Bank button and port 8/16 button on the front panel of

the switch.

Each SLAVE switch should now show a dash in its BANK display.

Now, reset the MASTER switch - it will show a 1 in the BANK display. Each SLAVE switch

BANK display will now change to a number according to its position in the daisy chain.