System Commissioning

This section of the manual is designed to be used with the
“Commissioning of Integrated Combo System” worksheet.
The worksheet is designed to guide you through the start-up
process in a logical, step by step method which should mini-
mize the work and time involved in having the system meet
the designed parameters.

The following conditions are assumed:

• The air filter is in place

• All supply diffusers and return grilles are fully open and

unrestricted

• Hot water is available to the furnace

• The drain valve for the heating loop is closed

• The shut off valves for the heating loop are fully open

• The throttling valve for the heating loop (if applicable), is

fully opened

• Electrical power is available at the furnace

• The return air temperature from the house is approxi-

mately 70°F (21°C)