Figure 14: critical hanger placement, Ents, Typical suspension details – Roberts Gorden Vantage twin Fire Unitary Infrared Heater TF-250 User Manual

Page 23: 17 figure 14: critical hanger placement

Advertising
background image

SECTION 7: H

EATER

I

NSTALLATION

17

FIGURE 14: Critical Hanger Placement

Hanger

Side View

Must Be Within 4" (10 cm)

Front View

S-hooks

Reflector

Hanger

45° Angle

* Allows for thermal expansion of system

Typical Suspension Details

Rod 3/8"

Beam Clamp

Concrete Beam

Wood Beam

Washers

Locknut

Screw Hook

3/8"

24" min.*

(61 cm)

“X”*

Anchor

S-hooks

Chain Size

3/16"

Minimum

Turnbuckle

Not Included

Description

Part Number

S-Hook

91907302

Tube/Reflector Hanger

03090100

Total Straight Length (both sides) or Length from U-Tube to U-Tube

in a Double "U" Layout

Typical Expansion

Each Side

Minimum “X” Length

0’ - 50’

±1” (3 cm)

12” (31 cm)

51’ - 60’

±2” (5 cm)

18” (46 cm)

61’ - 80’

±3” (8 cm)

24” (61 cm)

81’ - 100’

±4” (10 cm)

30" (76 cm)

101’ - 120’

±5” (13 cm)

36" (91 cm)

121’ - 140’

±6” (15 cm)

42" (107 cm)

141’ - 160’

±7” (18 cm)

48" (122 cm)

If the installation requires a shorter suspension length than the minimum listed, the suspension length
may be reduced by 6" (16 cm). In this case, tube clamps MUST be used at the two farthest hangers
on each side of the burner.

See Page 18, Figure 15.