INST

ALLA

TION

INSTALLATION

FRAMING

Diagram 2

Diagram 3

IMPORTANT

If converting this unit to LP, it is highly recommened the

conversion be done BEFORE the unit is slid into position

for ease of conversion. See "Conversion from NG to LP"

section for instructions.

Diagram 1

1) Frame in the enclosure for the unit with framing material. The framed

opening for the assembled kit is 45-7/8" high x 43" wide x 24-1/2"
deep (1143mm x H 1092mm W x 622mm D). See Diagram 1. Also
see Diagram 2 for corner installations.

IMPORTANT: Header must be metal stud. All other framing may
be of combustible type such as 2x4 / 2x6 framing materials.

Note: When constructing the framed opening, please ensure

there is access to install the gas lines when the unit is
installed. See Diagram 3 for details.

2) For exterior walls, insulate the enclosure to the same degree

as the rest of the house, apply vapour barrier and drywall, as
per local installation codes. (Do not insulate the fi replace
itself.)

3) The unit does not have to be completely enclosed in a chase.

You must maintain clearances from the vent to combustible
materials: See "Clearances" section. Combustible materials
can be laid against the side and back standoffs and the stove
base.

Framing

Note: The 24-1/2" fl ush framing depth (and the corner
framing installation) are based upon 1/2" drywall around
the perimeter of the fi replace on all three sides.