PNEG-1472 L & B Series Field Installation

13

If the dryer is to be set using a crane, a four point crane sling with a 10 ft minimum length must be used
to prevent excessive side pull on the crane brackets. The crane and sling should be sized to lift a
minimum of:

1. 3020L (C2130B) - 9,500 lbs

2. 4026L (C2140B) - 12,500 lbs

3. 6034L (C2160B) - 16,000 lbs

4. 7534L (C2175B) - 16,000 lbs

5. 1038L (C21100B) - 17,900 lbs

When the dryer is in position, place the 24” leg support assemblies evenly under the dryer as shown in
Figure 4A. Attach the legs using hardware items A and B , then lower the dryer body weight onto the
supports. Level and shim the dryer legs as required so that each leg is sharing the weight of the dryer.
The leg support assembly hardware can now be tightened.

The dryer body transport kit should now be removed. This includes the drop axle weldments and
wheels, hitch welment (6), hitch brace support (13), hitch brackets (8 & 9), hitch diagonal braces (11 &
12), and diagonal attaching channels (10). See Figure 4B.