12
PNEG-529 Cor-Lok and Cut-Lok Flooring for Non-GSI Bin Diameter
3. Flashing Installation
Figure 3A
Grain Systems Formed Flashing Installation
If bin sweep auger is to be used, overlap flashing such that rotation (usually clockwise) of the sweep will
climb up on the next flashing section. This will prevent the rotating/slipping outer wheel of the sweep from
catching on the flashing edges.
After the floor is in place, lay the flashing pieces on top of the floor place over the 1-1/4" bin bolts.
below to determine the correct sequence for placing the nuts and washers. Finger tighten
the nuts. While holding flashing flat, fasten the flashing to the floor with sheet metal screws. Now tighten
flashing nuts.
Figure 3B
Advertising