Flashing installation, Chapter 3 flashing installation, Grain systems formed flashing installation – Grain Systems Bin Flooring PNEG-529 User Manual

Page 12

Advertising
background image

12

PNEG-529 Cor-Lok and Cut-Lok Flooring for Non-GSI Bin Diameter

3. Flashing Installation

Figure 3A

Grain Systems Formed Flashing Installation

If bin sweep auger is to be used, overlap flashing such that rotation (usually clockwise) of the sweep will
climb up on the next flashing section. This will prevent the rotating/slipping outer wheel of the sweep from
catching on the flashing edges.

(See Figure 3A.)

After the floor is in place, lay the flashing pieces on top of the floor place over the 1-1/4" bin bolts.

See Figure 3B

below to determine the correct sequence for placing the nuts and washers. Finger tighten

the nuts. While holding flashing flat, fasten the flashing to the floor with sheet metal screws. Now tighten
flashing nuts.

(See Figure 3A

and Figure 3B.)

Figure 3B