PNEG-1092 30° Bin Roof Construction

Installation

8. If the roof sheet does not have a pre-punched hole for the roof vent, a hole must be cut. The cut hole

should match the roof vent. The hole’s inside edge should be approximately 15" from the eave.

(See Figure 4E.)

9. Place the three (3) foam strips on roof sheet, as shown in

Figure 4D

. Position roof vent over foam

strips and bolt down using 5/16" x 3/4" bin bolts and nuts. NOTE:

See Figure 4E

below for lower

two (2) bolts of vent.

Figure 4C

Figure 4D

Figure 4E