7. Farm Roof Assembly

PNEG-1092 30° Bin Roof Construction

29

Roof Assembly for 12' through 24' Bins (Continued)

To assemble slide rods and cover, insert straight end of slide rod through the center collar and thread one
5/16" nut all the way down on the rod. Then place rod through the cover and put a washer and nut on the
outside. DO NOT TIGHTEN. Insert rod through the cover, then place washer and nut on the outside.
TIGHTEN. Adjust and tighten nuts on straight end of rod. After tightening, it may be necessary to spread
the rods slightly to make them parallel. Maintain 10" between rods.

Figure 7E Section through Center Collar

Figure 7F Top View