6) inspecting for leaks in the fill-tub plumbing – Factory Direct Hardware Toto ABA990X#01FCP User Manual
Page 29

29
(6) Inspecting for leaks in the fill-tub plumbing
❈
If pressure leaks are discovered, run the test again after fixing the leaky areas.
• Do not apply additional pressure to the equipment.
➀
Install a valve on one end of the fill-tub plumbing. (Valve open.)
➁
Install a booster pump on the other end to feed water into the fill-tub plumbing.
➂
Once the air has been removed from the fill-tub plumbing and it has been filled with water, close the installed valve.
➃
Inspect for leaks.
Inspection pressure and time: 43.5 psi (0.30 MPa) for five minutes or longer.
• Use a pressure meter that suits the pressure being checked when inspecting the pressure.
• Be sure that there are no leaks or pressure drops across the gauge.
❈
Do not apply pressure to the equipment itself.
Caution
Inspection pressure and time: 43.5 psi (0.30 MPa) for five minutes or longer.
Booster pump
Gauge