Start-up and testing

36

5683EN-1

12.3.4

Chain elongation

During the run-in period, regular checks should be made to the elongation
of the conveyor chain. This is especially important if the conveyor is trans-
porting high loads or is of long overall length.

Regular inspections of the chain elongation are important. The chain
should be shortened after a run-in time of 40 hours. Further inspections
should be made at 200, 500 and then at 1000 hour intervals.