11. Position the other end bell on top and press

the end bells together.

12. Be careful not to pinch the tubing.

13. If end bells do not snap tightly together,

reload tubing.

14. If necessary, turn key in slot on rotor shaft to

adjust tubing (as in next step - E).

15. With key in slot on rotor shaft, turn key to

align tang on rotor shaft with slot in motor
drive shaft.

16. Point tubing retainer grooves up.

17. Shift the pump head slightly until it snaps on

the alignment pins (if present).

18. Secure with four provided screws.

19. Tighten with fingers only.

Figure 5-15: Pump Head Tubing Replacement

5.3.13 4-20 mA Adjustment Procedure

1. Select [TEST] from the Run Screen task bar, then, select

[SYSTEM DIAGNOSTICS].

2. Locate Analog A cursor and position the cursor to MAX

for a moment, then, return the cursor to MIN.