Installation & Maintenance Instructions

Installation

1. Remove the mixer and motor from the packaging and inspect for shipping damage.

2. Turn the shaft coupling and the motor coupling to verify there is no binding.

3. Adjust the mixer coupling so that the empty slots in the insert are at 3 and 9 o’clock.

4. Install the motor according to instructions in the appropriate motor manual.

5. Install into the container.

Maintenance

Disassembly

1. Loosen the set screw and remove the coupling half (item 2) from the top of the mixer shaft.
2. Gently hold the mixer tube (item 7) so as not to crush it, and use a 3/8” punch and hammer to drive the mixer
shaft up from the bottom until the bearing assembly (item 3) is exposed.
3. Use a 1/8” punch to remove the roll pin and slide the bearing assembly off the top of the shaft.
4. Remove the bottom bearing setscrew (item 13) and remove the bottom bearing (item 12).
5. Slide the shaft assembly down through the mixer tube and remove it out the bottom.
6. Remove the center bearing set screw (item 13) and remove the center bearing (item 10).
7. Remove and discard the seal assembly (item 4). Never re-use the seal assembly.

Inspection

1. Measure the inside diameter of the shaft hole on the bottom bearing (item 12) and the center bearing (item
10). If it is more than .425 it should be replaced.

2. Visually inspect the turbine assembly (item 11) for wear and replace if needed.

3. Inspect the shaft for wear in the center and bottom bearing areas, and inspect the shaft condition in the seal
(item 4) area.

4. Inspect the bearing assembly for rust, corrosion, or tightness and replace if needed.