AquaBlock 2 - Installation

17

AquaBlock 2 Installation Checklist

o

All users must carefully read and understand the Safety Precautions and all instructions before

using the AquaBlock 2 system.

o

Installation must comply with appropriate local, state, and national codes governing ventilation,

fire protection, operation, maintenance, and housekeeping. Refer to OSHA, NFPA-30, NFPA-33,

and the customer's insurance requirements.

o

All coating materials, solvents, etc. used in the AquaBlock 2 system must have a flash point of

equal to or above 100°F.

o

Filtration is required for the paint supply as well as any water or solvent supply connected to the

system.

o

All electrically conductive objects, with the exception of those required by the process, must be

grounded. This includes all metallic fluid lines, fittings, etc.

o

All connections to ground must be made individually from each component.

o

The ground lug on the AquaBlock 2 cabinet must be connected to ground.

o

The coating material supply to the AquaBlock 2 must be grounded.

o

An 18–24-inch length of electrically non-conductive fluid line must be used between the grounded

fluid supply and the AquaBlock 2 fluid inlet fitting.

o

The high voltage interlock from the AquaBlock 2 assembly must be installed and functional.

o

Main air supply to the AquaBlock 2 cabinet must be 90 psi +/- 5 psi.

o

The fluid inlet pressure at the AquaBlock 2 enclosure must never exceed 100 psi or be less than

20 psi.

o

The electrostatic voltage must never exceed 90kV.

o

Material to be sprayed in not of an emulsion typed.

LN-9902-00.3