Installation – Lincoln Electric IM10029 POWER WAVE S350CE User Manual

Page 18

Advertising
background image

A-9

INSTALLATION

POWER WAVE® S350CE

A-9

VOLTAGE SENSING
CONSIDERATIONS FOR MULTIPLE
ARC SYSTEMS

Special care must be taken when more than one arc
is welding simultaneously on a single part. Multiple arc
applications do not necessarily dictate the use of
remote work voltage sense leads, but they are strong-
ly recommended.

If Sense Leads ARE NOT Used:

• Avoid common current paths. Current from adja-

cent arcs can induce voltage into each others cur-
rent paths that can be misinterpreted by the power
sources, and result in arc interference.

If Sense Leads ARE Used:

• Position the sense leads out of the path of the weld

current. Especially any current paths common to
adjacent arcs. Current from adjacent arcs can
induce voltage into each others current paths that
can be misinterpreted by the power sources, and
result in arc interference.

• For longitudinal applications, connect all work leads

at one end of the weldment, and all of the work volt-
age sense leads at the opposite end of the weld-
ment. Perform welding in the direction away from
the work leads and toward the sense leads.

(See Figure A.7)

DIRECTION

OF TRAVEL

CONNECT ALL
WORK LEADS AT
THE BEGINNING
OF THE WELD.

CONNECT ALL SENSE
LEADS AT THE END
OF THE WELD.

FIGURE A.7

Advertising