INSTALLATION INSTRUCTIONS

for Vinyl Patio Doors without Nailing Fin (JII015)

4

INSTALL SILL PAN

PREPARE BUCK

3

4

7. Fold the three back

sides up to make a
3-sided box, and, for
step-down landings,
fold the front
flap down.

INSTALL SILL PAN

1. If installing a metal

sill pan on concrete,

cut a piece of self-

adhesive flashing

the length of the sill

pan and adhere it to

the entire bottom

surface where the

pan will sit on

the concrete.

2. Set the sill pan in

the rough opening,

aligning the front

edge (for continuous

slab) or folded down

edge (for step down)

with the exterior of

the rough opening.

3. Mark a line across

the front and back of

the sill pan.

4. Apply three 3/8"

beads of sealant

between the lines.

5. Place the sill pan in the rough opening. Firmly press the sill pan into

the sealant with a J-roller.

The sill can be prepared using one of two methods: We recommend
SureSill

Sloped Sill Pan

available from SureSill at www.suresill.com,

building supply stores, and some manufacturing locations. As an
alternative, a sill pan can be fabricated on site. If installing a SureSill

sill

pan, follow SureSill

’s instructions for installation and skip to section 4

“PREPARE BUCK“, or to section 5, “PREPARE STUD-FRAMED WALL“ as it
applies to your situation. If fabricating a sill pan on the job site, follow
the instructions below.

JOBSITE FABRICATED SILL PAN

1. Cut a piece of sheet

material to the
length shown.

2. Lightly crease folding

lines 1/2" in from the
two short sides and
one long side.

3. Measure the width

of the frame and
add 9/16".

4. Take this distance

from the back edge
and lightly crease a
folding line across
the sheet material.

5. For step-down

landings, cut 1/2"
in at this line on
both sides of the
sheet material.

6. For continuous slab, cut across the folding line.

Sealant

Frame

width

+9/16"

Folding Line

Length of rough opening sill plus 1"

1/2"

1/2"

Fold sides and back up

Fold corner

forward

Fold front

flap down

Remove for

continuous slab

Note!

This section applies to installations into a buck only. For

installations into a stud-framed wall, begin with section 5, “PREPARE
STUD-FRAMED WALL.”
1. Seal any joint larger than 1/16" in the buck and between the buck

and the concrete/masonry with sealant.

2. Cover the buck and the surrounding concrete/masonry at the head

and jambs (apply over sill pan if installing a job site fabricated sill
pan) with liquid applied flashing per manufacture’s instructions
as shown.

END of Buck Instructions, SKIP to section 6, “INSTALL DOOR.”