Figure 15 – Vaisala HMT360N User Manual

Page 35

Advertising
background image

Chapter 3 _______________________________________________________________ Installation

VAISALA _______________________________________________________________________ 33

0505-277

Figure 15

Installing the HMP368 Probe Through a Ball Valve
Assembly

The numbers below refer to

Figure 15 on page 33

:

1

=

Manual press tool

2

=

Handle of the ball valve

3

=

Probe

4

=

Process chamber/pipeline

5

=

Groove on the probe indicating the upper adjustment limit

6

=

Filter

7

=

Ball of the ball valve

NOTE

The probe can be installed in the process through the ball valve
assembly provided that the process pressure is less than 10 bar. This
way, the process does not have to be shut down when installing or
removing the probe. However, if the process is shut down before
removing the probe, the process pressure can be max. 20 bar.

NOTE

When measuring temperature dependent quantities make sure that the
temperature at the measurement point is equal to that of the process,
otherwise the moisture reading may be incorrect.

Advertising