FIGURE 7-1 CALIBRATION POTENTIOMETER AND JUMPER LOCATIONS (BACK OF GFC)

7.2

Calibration of GFC Mass Flow Controllers

All adjustments in this section are made from the outside of the meter, there is no
need to disassemble any part of the instrument.

GFC Mass Flow Controllers may be field recalibrated/checked for the same range
they were originally factory calibrated for. When linearity adjustment is needed, or
flow range changes are being made proceed to step 7.2.4. Flow range changes
may require a different Restrictor Flow Element (RFE). Additionally, a different
Solenoid Valve Orifice may also be required (see Table VI). Consult your distribu-
tor or Aalborg

7 for more information.

7.2.1

Connections and Initial Warm Up

At the 15-pin “D” connector of the GFC transducer, connect the multimeter to out-
put pins [1] and [2] for 0 to 5 VDC (or pins [9] and [14] for 4 to 20 mA) - (see Figure
2-1).

When using a remote setpoint for flow control, the appropriate reference signal
should also be connected to the 15-pin “D” connector at pins [8] and [10] - (see
Figure 2-1). Power up the Mass Flow Controller for at least 30 minutes prior to
commencing the calibration procedure.