7 commissioning, Commissioning the complete system, Commissioning the dgo – Festo Линейные приводы DGO, дюймовые User Manual

Page 25: 7commissioning

Advertising
background image

DGO−...−A−B

Festo DGO−...−A−B 0410b English

25

7

Commissioning

Commissioning the complete system

S

Always pressurize the complete system
slowly.

In this way you will prevent sudden
uncontrolled movements.
For slow start−up pressurization, use
start−up valve type HEL−.../HEM−... .

Commissioning the DGO−...

Warning

Make sure that:

Ĉ nobody can place his/her hand in the

path of the moving mass (e.Ăg. by
providing a protective grill).

Ĉ there are no objects in its path.

It must not be possible to touch the
DGO−... until it has come to a complete
stand.

1. Close both one−way flow control valves

ć at first completely,
ć then loosen them one turn.

Fig. 14

У

У

У

УУ

УУ

Fig. 15

Fig. 16