Transporting a suspended load, Leveling procedure – JLG 4017PS Operator Manual User Manual

Page 88

Advertising
background image

Section 4 - Operation

4-8

31200753

Transporting a Suspended Load

• Travel in accordance with the requirements set forth in Section 1 - General

Safety Practices and Section 5 - Attachments and Hitches.

• For additional requirements, refer to the appropriate capacity chart in the

operator cab.

Important things to remember:

• Ensure the boom is fully retracted.

• Never raise the load more than 300 mm (11.8 in) above ground surface or the

boom more than 45°.

• The combination of frame leveling and load could cause the telehandler to tip

over.

• The guide persons and operator must remain in constant communication (verbal

or hand) and be in visual contact with the operator at all times.

• Never place the guide persons between the suspended load and the telehandler.

• Only transport the load at walking speed, 0.4 m/s (0.9 mph), or less.

Leveling Procedure

1. Position machine in best location to lift or place load.

2. Apply parking brake and shift transmission to NEUTRAL.

3. Observe level indicator(s) to determine whether machine must be leveled prior

to lifting load. If equipped, level machine with frame level switch (see
page 3-25) or outrigger controls (see page 3-19 or 3-22).

4. Move boom so load is no more than 300 mm (11.8 in) above ground surface

and boom/or boom is raised no more than 45°.

OW0130

OZ3160

Advertising