9 second boom section assembly, Second boom section assembly – JLG G12-55A Service Manual User Manual

Page 47

Advertising
background image

3-13

G10-55A, G12-55A

Boom

3. Install the previously removed wear pad support

plates and spacers (7) with existing hardware at the
inside top front of the third boom section. Snug
mounting bolts. Shim as needed AFTER boom
section is installed to maintain a
0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

4. Install the previously removed wear pads, spacers

and shims on each side at the front of the third boom
section (8). Snug mounting bolts. Shim as needed
AFTER boom section is installed to maintain a
0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

5. Install the previously removed wear pad support (9)

at the front inside of the third boom section. Use the
previously removed hardened washers and bolts
(10). Torque as required.

6. Install the previously removed wear pads, spacers

and shims at the bottom front of the third boom
section (11). Snug mounting bolts.

Note: Longer bolts (12) may be required to fully engage
the threaded inserts in the wear pads without allowing
bolts to protrude past the chamfer on the wear pads.
Refer to page 6, Wear Pad Installation and Lubrication
for detailed information.

3.5.9

Second Boom Section Assembly

1. Place the second boom section onto suitable

supports.

2. Install the previously removed chain roller (13) at the

rear of the second boom section. Insert the mounting
pin, retainer plate and hardware. Torque as required.

3. Install the previously removed wear pads and

spacers (14) at the top rear of the second boom
section. Snug mounting bolts. Shim as needed
AFTER all boom sections are installed to maintain a
0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

4. Install the previously removed wear pads and

spacers (15) at each side rear of the second boom
section. Snug mounting bolts. Shim as needed
AFTER all boom sections are installed to maintain a
0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

5. Install the previously removed wear pads and

spacers (16) at the bottom rear of the second boom
section. Snug mounting bolts. Shim as needed
AFTER all boom sections are installed to maintain a
0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

6. Shims may be required to maintain a 0.070 - 0.130

in (1,78 - 3,30 mm) gap at the top rear of the second
boom section

MY3510

7

8

8

7

8

8

MY3510

9

12

11

10

12

10

11

MY4160

13

15

14

16

15

16

14

Advertising