10 third & fourth boom section installation, Third & fourth boom section installation – JLG G12-55A Service Manual User Manual

Page 48

Advertising
background image

Boom

3-14

G10-55A, G12-55A

3.5.10

Third & Fourth Boom Section
Installation

Note: Refer to Section 2.2, “Torque Charts,” for
standard bolt torque information.

Note: Refer to Section 2.2.3, “Hydraulic Hose Torque
Chart,” f
or standard hose torque information.

Note: Apply Loctite

®

242 to all boom assembly bolts.

Note: Using a straight bar approximately 40 in
(1041 mm) long will aid in the installation of the wear
pads located on the inside front of each boom section.

1. Place the sling or using two slings for better stability,

around the third boom section and slowly insert the
third and fourth boom sections into the second boom
section being careful not to damage any surrounding
components.

2. Install adjusting block (17) using existing hardware

(18). Torque as required.

3. Install chain & clevis (19), spring (20), spring stop

(21), adjusting nut and lock nut (22).

4. Allow 0.50 in (1,27 mm)(A) between the end of the

clevis (23) and the face of the lock nut (24). Torque
lock nut to 100 lb-ft (135 Nm).

5. Properly connect the battery.

6. Retract the second boom section pulling both retract

chains at the same time.

7. Install the previously removed wear pad support

plates and spacers (25) with existing hardware at the
inside top front of the second boom section. Snug
mounting bolts. Shim as needed AFTER boom
section is installed to maintain a 0.070 - 0.130 in
(1,78 - 3,30 mm) gap between the boom sections.

Note: Longer bolts may be required to fully engage the
threaded inserts in the wear pads without allowing bolts
to protrude past the chamfer on the wear pads. Refer to
Section 3.11.2, “Wear Pad Installation and Lubrication.”

8. Install the previously removed wear pads, spacers

and shims on each side at the front of the second
boom section (26). Snug mounting bolts. Shim as
needed AFTER boom section is installed to maintain
a 0.070 - 0.130 in (1,78 - 3,30 mm) gap between the
boom sections.

MY3540

18

17

19

18

21

22

20

A

MY3650

24

23

MY3450

25

25

26

26

MY3450

28

29

30

30

29

28

27

Advertising
This manual is related to the following products: