3121286
6. From Platform, pull Power/Emergency Stop
switch out.
7. Push the Engine Start switch until engine
starts.
NOTE:
Footswitch must be in released (up) position before
starter will operate. If starter operates with footswitch in
the depressed position, DO NOT OPERATE MACHINE.
Shutdown Procedure
IF AN ENGINE MALFUNCTION CAUSES AN UNSCHEDULED SHUT-
DOWN, DETERMINE THE CAUSE AND CORRECT IT BEFORE RESTART-
ING THE ENGINE.
1. Remove all load and allow engine to operate at low
speed for 3-5 minutes; this allows further reduction of
internal engine temperature.
2. Push Power/Emergency Stop switch in.
3. Turn Platform/Ground Select switch to Off.