PIT INSTALLATION – Platforms with Bevel Toe Guards
(Reference Figure 3A & 3B)

NOTICE !


When moving the lift, do not attempt to pick it up by the platform; it
is hinged and could be damaged. Pick up the lift from under the
base frame ONLY using a strap sling.

5. Make temporary electrical connections and permanent hydraulic connections. Raise

the lift approximately one foot using the “UP” button. Then lower the lift back to fully
collapse, holding the “DOWN” button for approximately 60 seconds. Repeat this
process five to seven times to bleed any air out of the hydraulic system.

6. Raise and lower the lift to make positioning adjustments and align the platform in the

pit with a proper clearance of 1" minimum between the platform edge and the pit
curb angle.

DANGER

!

Do not work under lift without Maintenance Device! To avoid
personal injury, NEVER go under the lift platform until the load is
removed and the scissors mechanism is securely blocked in the
open position and the appropriate OSHA lock-out/tag-out
procedure is followed. See "Lift Blocking Instructions" section.

7. The base frame of the lift has pre-drilled holes for lagging it securely to the floor.

Mark hoes, drill, and install with anchors. Lifts with oversize platforms have
minimum pull out requirements of 2,000 lbs. for each anchor.

8. Make the permanent electrical connections and operate the lift through a few cycles.